Why the slag discharge tube of circulating fluidized bed boiler will be blocked?

12 Jul 2018

(Details on the problem) Specific Performance:

Slagging pipe blocks during operation of circulating fluidized bed boiler.

Answer:cause of failure:

(1) The internal shape is caused by the limited expansion of the wear-resistant material inside the slag discharge pipe. The internal components of the slag cooler are deformed, affecting the fluidization of the slag cooler; the slag cooler is deactivated for a long time or a single slag cooler is selected for slagging, and the bed material in the deactivated slag cooler is bonded under the influence of steam, which being low temperature coke.

(2) The operating personnel did not grasp the ratio of the fluidized air volume of the slag cooler. Inappropriate air volume ratio resulted in poor ash slag fluidization in the slag cooler.

Troubleshooting:

(1) Operation personnel should strengthen understanding of boiler operating conditions, adjust boiler parameters in a timely manner, set up the concept of boiler material dynamic balance, control boiler operating bed pressure at normal values, and try to avoid large boiler slag discharge.

(2) The slag cooler hood should be purged each time the boiler is stopped. It is found that the blocked hood must be opened to control the size of the fuel.

(3) Boiler slagging, slag cooler should be carried out alternately; the slag entering the slag cooler should be fully cooled to ensure the working conditions of slag cooler.

(4) Summarizing the experience of the fluidization air volume of the slag cooler, select the optimization parameters of the squid air volume in each plenum, including the lowest fluidization air volume of the slag cooler to ensure the normal fluidization of the slag cooler under any load.

 

Products Recommended
WNS series gas-fired (oil-fired) steam boiler 1-20 t/h
Pressure: 0.7-2 Mpa
SZS series gas-fired (oil-fired) hot water boiler 7-116 MW
Pressure: 1.0-1.6 Mpa
WNS series gas-fired (oil-fired) hot water boiler 0.7-14 MW
Pressure: 0.7-1.25 Mpa
SZS series gas-fired (oil-fired) steam boiler 10-100 t/h
Pressure: 2.5-9.8 Mpa
Success Stories
14 MW WNS condensing gas-fired boiler for university
14 MW WNS condensing gas-fired boiler for university Equipment: 3 sets of WNS14-1.0/115/70-Q, 2 sets of WNS6-1.0-Q
Capacity: 14 MW, 6 tph
30 tph steam boiler for starch plant
30 tph steam boiler for starch plant Equipment: condensing gas fired steam boiler
Capacity: 30 tph
2 tph WNS condensing gas-fired steam boiler for chemical industry
2 tph WNS condensing gas-fired steam boiler for chemical industry Equipment: WNS2-1.25-Q
Capacity: 2 tph
20 tph SZS condensing gas-fired steam boiler for paper industry
20 tph SZS condensing gas-fired steam boiler for paper industry Equipment: SZS20-2.5-Q
Capacity: 20 tph
Checking Order Quality Test Before Delivery Check Items When Packing Packaging And Transport
Get An Instant Quotation

For all inquiries, please fill in the form below (* are required) to send us a brief message, and we will get back to you as soon as possible.

Product:
* Email:
Tel:
Name:
Boiler fuel:
  • Gas
  • Oil
  • Biomass
  • Coal
  • Waste Heat
  • Other
Application:
  • Textile Industry
  • Central Heating
  • Food Plant
  • Power Plant
  • Chemical Industry
  • Waste Heat Recovery
  • AAC Block Plant
  • Hotel & Resort
  • CHP
  • Other